WESTGATE DOCTORS SURGERY,6 NO NEW CONSULTING ROOMS AND INTERNAL REFURBISHMENT, WESTGATE BAY AVENUE WESTGATE ON SEA, KENT

Project Value £ 350,000.00
Project Architect: Duncan and Graham – Simon Friend 
Client: Westgate Surgery 

Project Commenced 16/01/2012
Project Completion Date 28/09/2012 

BEC SITE MANAGER: Mr Andy Louch 

Traditionally constructed Facing Brick Extension, Eco Joist roof, Single Ply Roof Finish, with Wood Effect UPVC windows. Internally 6 No treatment and consulting rooms. Exisitng Surgery refurbished with new Reception, front entrance, and extensive external works Foundations and oversight.

  
  C.A.T.S College
  

C.A.T.S COLLEGE NEW INFILL TEACHING BLOCK, 56-60 NEW DOVER ROAD, CANTERBURY, KENT

Project Value £ 700,000.00
Project Architect: Clague Architects – Pat Mills
Client: C.A.T.S College – Mr Sherif Elmaourki 
QS Betteridge & Milsom 

Project Commenced 16/01/2012
Project Completion Date 31/08/2012 

BEC SITE MANAGER: Mr Doug Woodcock.

New Timber framed Building to provide 6 No new Classrooms. Construction consists of traditional foundations, PCC floor, Kingspan timber frame, and underfloor heating, and Single Ply roof to the main block. External faced brickwork, with brick arches, Aluminium windows, with extensive external works. Scheme constructed to Breeam Very Good, and under the CCS scheme.

C.A.T.S College   C.A.T.S College

C.A.T.S College  C.A.T.S College 

BAY POINT GYM, EXTENSION, SANDWICH KENT

Project Value £ 200,000.00

Project Architect: URBAN SURVEYING

Client: BAY POINT GYM

Project Commenced 16/06/2012 
Project Completion Date 28/09/2012

BEC SITE MANAGER: Mr JOHN VERRIER

Traditionally constructed, facing brick extension, metal fabricated trusses, composite insulated roof finishes, with aluminium windows.

Internally, new flooring, and fit out for new gymnasium.

  

EXTENSION TO MINSTER PRIMARY SCHOOL, MINSTER, RAMSGATE, KENT

Project Value £ 250,000.00
Project Architect: BAILEY PARTNERSHIP 
Client: KCC

Project Commenced 27/08/2012 
Project Completion Date 21/12/2012

BEC SITE MANAGER: Mr GLENN PARKER

New traditionally constructed building to provide additional teaching and flo offices, of traditional foundations, pcc floor, under floor heating, and tiled roof with solar panels. External faced brickwork, aluminium windows, with extensive external works.