THANET WINDFARM – EXTENSION TO THE EXISTING THANET WINDFARM OFFICE BLOCK
Project Value £1,100,000.00
Project Architect: DUNCAN AND GRAHAM PARTNERSHIP
Client: VATTENFALL
Project Commenced
Project Completion Date 10/07/2015
BEC SITE MANAGER:
Traditionally constructed Extension’s to the existing building to provide additional office space, kitchen, drying rooms, changing facilities. The project consisted of a New Car Park, and two new two Storey extension, constructed from piled foundations, load bearing facing blockwork, and steel frame, pcc ground and first floors, with timber roof. Finishes are a tiled roof, with integral pv, facing blockwork, with new aluminium doors, and windows.
![]() |
![]() |
![]() |
![]() |
KENTISH FLATS – EXTENSION TO WINDFARM OFFICE BLOCK
Project Value: £1,100,000.00
Project Architect: DUNCAN AND GRAHAM PARTNERSHIP
Client: VATENFALL
Project Commenced 10/11/2014
Project Completion Date 10/7/2015
BEC SITE MANAGER: ANDY LOUCH
Traditionally constructed Extension’s to the existing building to provide additional office space, kitchen, drying rooms, changing facilities.
The project consisted of a New Car Park, and two new two Storey extension, constructed from piled foundations, load bearing facing blockwork, and steel frame, pcc ground and first floors, with timber roof. Finishes are a tiled roof, with integral pv, facing blockwork, with new aluminium doors, and windows.
PILING WORK | FOUNDATIONS POURED |
![]() |
![]() |
PCC FLOORS | STEEL FRAME ERECTED |
![]() |
![]() |
NEW PURPOSE BUILT STEELPLAN KITCHEN | NEW LOCKER ROOM |
![]() |
![]() |
NEW FEMALE LOCKER ROOM | NEW OFFICE |
![]() |
![]() |
NEW PRESENTATION ROOM | DRYING ROOM |
![]() |
![]() |
![]() |
![]() |
BARHAM VILLAGE HALL - EXTENSION
Project Value: £575,000.00
Project Architect: GODDEN ALAN LAWN
Client: BARHAM VILLAGE HALL
Project Commenced 12/1/2015
Project Completion Date 7/8/2015 –
BEC SITE MANAGER: MR PATRICK BROADHURST
Traditionally constructed Extension’s to the existing village hall to provide a Post Office, extended hall, wc’s, kitchen, and reception and coffee room.
The project consisted of a New Car Park, and new single Storey extension, constructed from strip foundations, load bearing facing blockwork, and steel frame, in-situ concrete ground floors, with timber roof. Finishes are a tiled roof, with pv, roof windows, facing blockwork, with new aluminium doors, and windows, and external render.
FOUNDATION EXCAVATION | GF SLAB AND BLOCKWORK |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
JUNIOR KINGS SCHOOL – EXTENSION TO PROVIDE NEW MUSIC BLOCK
Project Value: £1,100,000.00
Project Architect: BDB ARCHITECTS
Client: JUNIOR KINGS SCHOOL
Project Commenced 12/1/2015
Project Completion Date 04/09/2015 –
BEC SITE MANAGER: Mr GLENN PARKER
Traditionally constructed Extension to the existing school building to provide 10 practise rooms, one classroom, and one recital room.
The project consisted of a New Car Park, and two new two Storey extension, constructed from piled foundations, load bearing facing brickwork, and steel frame, pcc ground and first floors, with timber roof. Finishes are a tiled roof, with pv, facing blockwork, with new aluminium doors, and windows.
PILING TO FOUNDATIONS | FOUNDATIONS READY TO BE POURED |
![]() |
![]() |
![]() |
![]() |
NEW RECITAL HOUSE | NEW CLASSROOM |
![]() |
![]() |
NEW STAFF KITCHEN | NEW BUILD |
![]() |
![]() |
![]() |
![]() |
FEGANS FAMILY CENTRE – NEW BUILD DESIGN AND BUILD PROJECT TO PROVIDE NEW NURSERY, AND HALL
Project Value: £1,250,000.00
Project Architect: BEC & DUNCAN AND GRAHAM
Client: FEGANS
Project Commenced 04/03/2015
Project Completion Date 18/12/2015 –
BEC SITE MANAGER: Mr STEVE HOARE
Traditionally constructed New Build Family centre.
The project consisted of a New Car Park, and a new single storey stand alone building, constructed from strip foundations, load bearing facing blockwork, and steel frame, pcc ground floor, and a trussed timber roof. Finishes are a insulated profiled roof, with pv, facing blockwork, with new aluminium doors, and windows.
DEMOLITION OF ORIGINAL BUILDING | STEEL FRAME BEING ERECTED |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |